Thumbnail Image for Article 19348Mar. 9, 2018 Bond Update
Posted Date: 03/09/2018

At Robert Martin Elementary, the masons on the classroom addition brought all 12” storm shelter walls up to structural bearing height, grouted them and have moved on to the smaller 8” interior load bearing walls in the corridor. The remaining beams for the roof structure arrived and a crane will be on site in the upcoming week or two to start flying steel. 

RMES 3-9-18 RMES 3-9-18 beams

The turf at the Andover High School baseball field is nearing completion.

ahs turf 3-9-18

The block is complete at Wheatland Elementary and the structural steel for the roof has started.

WES 3-9-18

Block walls are finishing up this week at Prairie Creek Elementary.

PCES 3-9-18