Feb. 9 Bond Update


Posted Date: 02/09/2018

Thumbnail Image for Article 18410

Construction continues across the district. 

The crew at Robert Martin Elementary has been working on the concrete for the classroom addition. They have also started demolition for the cafeteria addition.

Crews began removing rock from the roof at Andover Central Middle School in preparation for the reroofing project.

Footings have been poured at Sunflower Elementary School and the slab on grade will be poured later.

Masonry has started at Prairie Creek Elementary.