Bond Updates ➤ Article 18789
Thumbnail Image for Article 18789Feb. 23 Bond Update
Posted Date: 02/23/2018

The masonry crew got started at Robert Martin Elementary laying block for the FEMA structure and have completed laying all exterior 12” block walls up to 8’-0”. Inside, the Hutton Construction crew put together a display in the commons to teach the kids and generate excitement.

RMES walls  RMES signed beam

Lots of activity at Cottonwood Elementary as Hutton crews poured the concrete slab on grade.

CES pour

The turf for the Andover High School baseball and softball fields was delivered this week.

AHS turf

Masonry is 75% complete for the classroom addition at Wheatland Elementary School.

WES Walls 2-23