Bond Updates

Thumbnail Image for Article 21946

May 25, 2018 Bond Update

Posted Date: 05/25/2018

Playground equipment is being installed at Sunflower Elementary. At Robert Martin Elementary, the crews began demolition and dirt work at the front administration entry to get a head start on . . .

Read Full Article

Thumbnail Image for Article 21781

May 18, 2018 Bond Update

Posted Date: 05/18/2018

Last week, the construction team met one of their milestones on the construction schedule by getting the building “dried –in”, which means there is a roof and water should not enter the building if . . .

Read Full Article

Thumbnail Image for Article 21691

May 2018 Bond Video

Posted Date: 05/15/2018

Check out the latest drone video of the progress on the bond projects. . . .

Read Full Article

Thumbnail Image for Article 21625

May 11, 2018 Bond Update

Posted Date: 05/11/2018

At Robert Martin Elementary, the roofers made a great attempt to complete the roof over the storm shelter but high winds and rain slowed them down and they only completed about half of the building. . . .

Read Full Article

Thumbnail Image for Article 21399

May 4, 2018 Bond Update

Posted Date: 05/04/2018

SJCF kicked off the design process this week at meetings with the entire staff at Meadowlark Elementary. One of the items they learned about was critical spatial relationships to other . . .

Read Full Article